Green roof

Green roof build-up, gravel border, paths and fire divider strips. Quantities of substrate, drainage, gravel and trims, and the saturated load.

What the green roof calculates

The module issues quantities of the green roof build-up: the substrate area and volume, vegetation, drainage, root barrier and textiles, gravel, trim heights and lengths, and the saturated weight of the build-up. It does not assess the structural design, the fire safety of the building or the drainage of the green roof.

Before you start, you need a roof drawn with a scale. In the default levelling mode, you also need calculated slopes (see below).

1. Open the green roof editor

  1. In the project cockpit, open the Calculations tab.
  2. On the Green roof card, click Open the green roof.
  3. On the left is a panel like the one for anchoring and slopes: at the top the roof switch with the status mark, a step with a sentence, a Status card with three numbers (Vegetation / gravel, Substrate volume, Saturated weight), Tools and view, Set the build-up… and at the bottom the main button Calculate quantities. The roof plan is on the right; details open in the Quantities and findings… and Customer plan… windows.

Green roof editor: the left panel and the roof plan with gravel along the perimeter and around an opening

2. Build-up

  1. Click Set the build-up…. The Green roof build-up window opens in three steps: Build-up, Levelling and Gravel and fire strip. When inputs are missing, the button is amber and reads Complete the build-up.
  2. In the Build-up step, select a build-up in the Catalogue build-up field. The build-up prefills the layer thicknesses. For your own values, choose No build-up (manual entry).
  3. In the Levelling step, choose the Substrate levelling mode:
    • Global level plane (default): the substrate levels out the slopes to a plane. The volume is calculated from the thickness bands of the slopes, so the slopes must be calculated.
    • Follow the slope: the build-up has the same thickness everywhere and does not need the slopes.
  4. Fill in Min. substrate thickness (mm), Vegetation layer thickness (mm), Vegetation type (Sedum mat or Cuttings) and the other thicknesses.
  5. In the Gravel and fire strip step, check Default gravel strip width (mm) and Min. fire strip width (mm).
  6. Click Save. Cancel, the cross and Esc close the window without saving. The Build-up…, Levelling… and Strip widths… rows in the panel show what applies.

If you edit a catalogue build-up manually, saving detaches it from the catalogue and your thicknesses apply from then on. The editor warns you about this.

3. Gravel border

In Tools and view there are four tools: Gravel (default), Path, Select and Delete. A sentence below them says what the tool does.

  • The application creates the gravel border along the perimeter and around openings by itself. With the Gravel tool, click an edge or an opening in the plan to add or remove it.
  • In bulk: Add gravel with the options Whole perimeter, All openings and Squares at drains. For a drain, you enter the side of the square, and the gravel lies over the drain as a square.
  • With the Select tool, click an edge, an opening or a path, and the element card appears on the left. An edge or opening without gravel can be selected too: the card offers Add gravel. A click on an empty place clears the selection. On a roof with several polygons, edges are numbered polygon.edge.
  • On the element card you change the Strip width (mm). An empty field = the default width from the build-up.
  • The Gravel and paths list below the card lists all elements, and a click selects one.
  • The Delete tool removes the gravel at an edge or opening, or a path.
  • Gravel and paths are saved with the Calculate quantities button at the bottom of the panel.

An opening of the Plant / equipment type (for example an HVAC unit on feet) is calculated differently from other openings: the area under it is not deducted, and the whole footprint under the unit is gravel, without vegetation.

If the geometry changes and a marked element disappears, the editor shows Marks without an element. Remove them with the Remove marks without an element button.

4. Paths and divider strips

  1. Choose the Path tool. In its options, choose the Purpose: Walkway or Fire divider strip. Enter the Path width (mm).
  2. Draw a polyline by clicking in the plan.
  3. Enter or a double-click finishes the path, Esc cancels drawing, Backspace removes the last point.

Fire safety rules

  • A continuous vegetated area must not exceed 1,500 m². Divide a larger area with a fire divider strip at least 2 m wide, otherwise the take-off is not issued.
  • Perimeter strips, gravel around openings and fire divider strips must not be narrower than Min. fire strip width. The usual value of 500 mm, and at least 300 mm for lower-risk details, comes from an informative methodology. The binding solution is set by the fire safety design of the building.
  • The application does not know the boundaries of the fire compartments below the roof. Dividing the roof according to them is up to the designer.

5. Quantities

The Quantities window opens with the Quantities and findings… link in the status card. It shows:

  • Vegetation, Substrate area, Substrate volume, Drainage, Root barrier + textiles and Saturated weight in tonnes,
  • Gravel: volume and weight for the perimeter strips, the gravel around openings, the fire divider strips and the walkways,
  • Edge trims: Dividing trim (green / gravel) and Gravel stop (free drainage edge) by height.

The trim is as high as the build-up up to the top of the substrate, the vegetation layer is not counted. The height is rounded up to the next 10 mm. If it cannot be calculated (for example, the build-up does not state the thickness of a layer), the application does not state it and says why.

Outputs

  • Reports tab: the Green roof chapter, and in the Documents for suppliers section the Green roof card with the Supplier document PDF – green roof and Overview for ordering and quotation (CSV) documents. The quantities are net, without waste and reserve.
  • Customer plan… (a link in the status card): the Create preview button creates a colour plan of the planted area and the gravel, Download image saves it.

When to recalculate

After a new slope calculation or a change of the roof, the result is out of date. In Global level plane mode, the substrate thickness bands no longer apply. The Status card then says Quantities out of date, calculate again. Open the green roof editor and click Calculate quantities. The same applies after you change the gravel or paths until you save them.

Pass the saturated weight on to the structural engineer. FredIQ does not assess the structural design, see What FredIQ does not assess.